Friday, November 15, 2024
30.0°F

Whitefish Mountain Resort sees progress on new chairlift installation

by WHITNEY ENGLAND
Whitefish Pilot | July 13, 2022 1:00 AM

Work is well underway on installing the new six-person chairlift at Whitefish Mountain Resort.

Last week crews closed a large portion of the mountain on Friday as a Black Hawk helicopter hauled wet concrete and concrete forms to the top of Inspiration Ridge. Forms were set and workers poured concrete that will become the top terminal of the new Chair 4 that is planned to open for the 2022-23 winter season.

Whitefish Mountain Resort says the second day of concrete work for the new chair will take place on Thursday, July 14. This work was originally scheduled to occur a day later but was moved to Thursday due to scheduling conflicts.

Thursday's work will begin at 6 a.m. and should be completed by the time most mountain activities open for the day.

“The chopper will be moving concrete forms from the Fir parking lot to several tower placements on the mountain,” Whitefish Mountain Resort officials said.

The new Chair 4, dubbed the Snow Ghost Express, will provide direct access to the upper terrain at Whitefish Mountain Resort and help alleviate traffic on other lifts, according to the resort. As most of the parking is located at the Base Lodge area, the new six-pack lift will take guests up the mountain quicker without the need to ride beginner lift Chair 6 to reach Chair 1 for transport to the summit. A trip on the new lift will last 7 minutes and cover 2,200 vertical feet.

The old Chair 4 was a much smaller lift that crews recently removed; that chair was installed in 1978 before the Base Lodge was built.

The company building the Snow Ghost Express lift line is Leitner-Poma of America which is headquartered in Grand Junction, Colorado, and has been charged with several chairlift and gondola projects across the country over many years. Leitner-Poma has been working on the lift for several months and poured concrete foundations for several of the 25 towers that will support the new lift.

As work continues, partial closures of the mountain and some summer activities could occur. Last Friday WMR closed Chairs 1 and 10, the Summit House, Zip Line Tours, the Danny On Trail and all mountain biking trails due to the concrete work and the helicopter overhead.

In other news, the resort also recently announced that Chair 1 mountain biking trails for advanced and expert riders opened Monday. The resort says that intermediate trails from the summit will require significant reroutes and will open as soon as possible, but likely not until August.

photo

Construction workers pour foundations for Whitefish Mountain Resort's new Chair 4 on Friday, July 8. (Photo courtesy of Whitefish Mountain Resort)